May 26, 2004

Independent Review Panel Releases Report On Mt. Tabor Reservoirs

Presents Majority And Minority Opinions Of The Panel

As expected this week, the Mt. Tabor Independent Review Panel has released its report (pdf) detailing its split decision in which eight members supported a "risk mitigation" option, and five members supported burial.

(Note: As explained on the Mt. Tabor IRP website, that above-linked pdf includes the Report and Appendices A, B, C, F, and G. Readers can also view Appendix D separately, but Appendix E, which consists of materials submitted to the panel by the public is still being compiled.)

In its deliberations, the panel discarded other options for the Mt. Tabor reservoirs, including: buried reservoirs without park improvements ("eliminated because of the adverse impact on and aesthetic degradation to Mt. Tabor Park"); treatment at the reservoir outlets ("eliminated because of its excessive expense to water users and the resultant cost to the Parks Bureau to move an existing maintenance yard"); removing reservoirs from use and seeking replacement storage ("eliminated because of its potential adverse impact on system reliability"); and a panel-proposed option to "do nothing" with the reservoirs ("eliminated because the Panel felt some action is required to ensure water safety").

Major findings from the panel's majority, in short form, are as follows and are taken verbatim from the report:

  • Water quality in Portland is very good and meets all current federal regulations.
  • There is a very low risk that a terrorist act would harm the City's water supplies.
  • Vandals can access the water supplies, but are not likely to introduce an agent that would undermine the health of system users.
  • Water rates are expected to rise steadily over the next decade, well ahead of the rate of inflation.
  • Water usage in Portland is declining.
  • There is no current federal or state regulation requiring that the reservoirs be buried.
  • New federal regulations are in development, but are not yet complete. They could impact many aspects of the Portland water system, not just Mt. Tabor, but are not expected to ban open reservoirs systems.
  • The reservoirs are a critical part of the history and character of Mt. Tabor Park.

See the full report for more detailed explanations of each of these findings. Worthy of note is that even within the majority, there was some differing opinion:

A majority of the Panel's members have determined that there is no compelling reason to bury the reservoirs at this time, nor may there ever be a compelling reason to bury them. Some members of the Panel majority believe all plans to eliminate open storage should be rejected permanently. Other majority members acknowledge that regulatory changes or other factors may lead to a decisioneliminate it now.

Based upon the majority's findings, it offers the following set of seven recommendations, taken verbatim from the report:

  • The City Council should adopt a risk management strategy to ensure the safety and quality of drinking water supplies at Mt. Tabor Park.
  • Since a specific risk mitigation plan was not provided in the Council resolution, a risk mitigation plan will need to be determined and considered by the public prior to City approval.
  • A risk mitigation strategy should preserve the historic character of Mt. Tabor Park and adhere to the Mt. Tabor Park Master Plan.
  • The City Council should revisit this issue in the future, potentially when new federal rules are finalized, or state rules enacted.
  • Deferred maintenance at the reservoirs and elsewhere in the water system should be reviewed, and work completed where it is necessary to maintain the integrity of the reservoirs and the water delivery system.
  • Potential changes to Mt. Tabor should not be considered in isolation. Rather, the City should consider all upgrades necessary as a result of any new regulation in a holistic manner, calling upon experts and community representatives to assist the city in devising a plan that meets regulatory requirements, maintains safe and reliable supplies and assures long-term affordability of the City's water services.
  • Rate impacts should be minimized.

In the end, the majority opinion recommends that the City Council pursue "variations" on the two risk mitigation options presented to them, one of which was a proposal for risk mitigation from the Friends of the Reservoirs. "The Panel majority feels," says the report, "that additional measures at this time are not warranted given the limited risks on the system and the high costs that would be borne by ratepayers."

While the Panel did not have any real opportunity to examine possible risk mitigation strategies, it does offer several areas for possible consideration and further discussion, including additional security, better water-monitoring technology, animal control, and fencing. Interestingly, on that last item, the Panel specifically rejected its consultants' recommendation that a massive 40-yard perimeter would be required around the reservoirs.

As for the minority opinion -- which takes up all of two pages in the report, as compared to the eight pages for the majority opinion -- it says that its preference for burial was based on the following considerations: reservoir condition; location and gravity distribution; industry standards; water quality; intentional threats to water safety; terrorism; historic preservation; enhanced recreation and aesthetics; and cost.

With those considerations in mind (see the report for their "full" explanations), the Panel's minority recommended the following, which is taken verbatim:

  • Retire Reservoir 1 from use as drinking water storage, and restore and maintain the facilities on top as they currently exist, or in accordance with Parks Bureau guiding principles.
  • Bury two enclosed tanks beneath Reservoir 5 under the existing perimeter, and restore and maintain the facilities on top exactly as they currently exist.
  • Bury enough storage to provide 20 MGD beneath Reservoir 6 North; the remainder of Reservoir 6 should be restored and maintained consistent with values and design guidelines established in the Mt. Tabor Master Plan and guiding principles.
  • Do not replace lost storage capacity at Powell Butte or elsewhere, as it does not appear to be needed.

Now, it's not that we're intentionally giving short shrift to the minority opinion here. But they appear to do less than half the actual explanatory work done by the majority members in presenting their opinion and recommendation. One would think, with all of the discussion and debate both prior to this Panel's institution and during its existence (and especially given how much the lack of quality or quantity of proper discussion on the reservoirs has been an issue during this long controversy), that the minority might have thought to strongly -- or, Hell, even adequately -- detail its rationales.

To our reading, the minority opinion seems to partake of the same non-arguments that the Water Bureau and its own consultants themselves have been pitching since the beginning, wherein simple declaratory statements that something needs to be done as considered to be evidence enough, no further explanation or evidence required.

Hopefully, the City Council will take that into consideration when they decide what to do with the Panel's conflicting set of recommendations. It seems fairly evident to us that while the majority goes out of its way to demonstrate its case, the minority simply states that they are the ones who are correct.

That's the same sort of nonsense that started this entire mess to begin with, and now that the City Council will have a document in hand -- that being the majority opinion from the Panel -- which provides them some actual considered argument, they would be wise to heed it.

« Previous Next »

Comments (7)

  1. Michael the Archangel on 26 May 2004

    Let's see, the findings of this review are a surprise because of why???

    It's like everything else, the majority of the population doesn't want it, city hall does want it, who wins??? City hall.

    We didn't want the MLK toy train, city hall did, we got that toy train. We don't want a toy train out to Clackamas, they do, we're going to waste money it.

    Goodbye reserviour and hello more taxes and more useless spending.

  2. Bob R. on 26 May 2004

    I know this is a tangent, but Michael brought it up, so...

    I don't recall one person attending the numerous public hearings and workshops on light rail expressing opposition to the Clackamas extension of light rail.

    Why "Toy Train"? What is your threshold definition for "Real Train"?

    And just in case you weren't paying attention: I-205 was planned and constructed, decades ago, with additional right-of-way for future dedicated transit. Which is what Clackamas light rail will be using from Gateway on south, allowing for relatively low construction costs.

    - Bob

  3. Keith on 27 May 2004

    I vote for public officials to listen to public input, then make the tough decisions. Should they only do what the majority of the people want? Or only what is most popular? They are expected to be the ones with the bigger picture (funding, planning, the future), and should be acting in the best interest of all citizens, and not just those who are the most vocal, or only what the majority wants. The majority gets to have its say, by voting them out of office when the time comes; why isn't that enough power?

  4. The One True b!X on 27 May 2004

    I vote for public officials to listen to public input, then make the tough decisions.

    Which of course is why the Panel was created -- because everyone who was not in fact listened to at all when before the decision was made caused noise about this fact (and about the fact that the Water Bureau's consultants had been, in essence, stacking the deck).

  5. JJ on 27 May 2004

    I still can't figure out WHY we are doing this.

    There are sooo many gallons of water it would take semi after semi after semi tankers full of toxic chems dumped into the reservoirs to contaminate enough to have *any* effect. First, they would have to GET the chemicals. I would imagine the feds are watching the legit suppliers of Ricin and Cyanide (they do have commercial applications after all), and would be alerted if say, a dozen tankers were filled up, paid for in cash, and had no apparent destination.

    Poisons dilute in the water. Simple hydrology. Ricin is the most effective, but there would have to be soooo much dumped that it would be an almost impossibility.

    The simplest solution is to block off the park so that NO semi could edge its way within 100 yards of the reservoirs. And then move the fence back another 15 or 20 feet from each reservoir to guard against random urination, and you would be set (more or less).

    Maybe have the neighbors watch out for suspicious activity. A neighborhood watch for the park.

    Of course, that means the police would have to patrol via motorbike or horse, and the parks department would have to figure out how to get in mowers and equipment, but that would CERTAINLY be cheaper than covering or burying and maintaining closed tanks.

    I love government.

    jj

  6. pdxkona on 28 May 2004

    That's a really good point JJ.

    I would like to see an unbiased, outside source be consulted into the exact biological and chemical 'risks' we are currently running. I want to know exactly what kind of various chemical possiblities would make a nonexistent,small or large impacts; I want graphs, I want stats. I want to know what exactly we are working with here; isn't this what risk assessment is all about?

  7. The One True b!X on 28 May 2004

    Well, look around in the presentation materials which comprise Appendix D.